Keyera has started up all six of its gas plants that were shut-in last month due to wildfires.
The Calgary, Alberta-based energy company said Friday that the production disruption is expected to impact the operating margin of its gathering and processing segment by 13 million Canadian dollars ($9.73 million) to C$15 million.
Due to the disruption, a 10-day turnaround at the company’s Wapiti gas plant that had been planned for the second quarter has been pushed to the fourth quarter.
A three-week turnaround at the company’s Rimbey gas plant in the second quarter will continue as planned, Keyera said.